0
Skip to Content
The Historic Bell Barn of Indian Head
About Us
Our Museum
Board of Directors
History
Venue Bookings
Our Wedding Venue
Event Bookings
Request Booking
Horse Fair Vendor Application
Historical Archives
Education
Programs
Resources
Tours
Events & Tickets
Donate & Volunteer
Donate & Volunteer
The Historic Bell Barn of Indian Head
About Us
Our Museum
Board of Directors
History
Venue Bookings
Our Wedding Venue
Event Bookings
Request Booking
Horse Fair Vendor Application
Historical Archives
Education
Programs
Resources
Tours
Events & Tickets
Folder: About Us
Back
Our Museum
Board of Directors
History
Folder: Venue Bookings
Back
Our Wedding Venue
Event Bookings
Request Booking
Horse Fair Vendor Application
Historical Archives
Folder: Education
Back
Programs
Resources
Tours
Events & Tickets
Donate & Volunteer
c0078-Bell-Barn-Restoration-473-Dan-Loran-Dec-03,-2009
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0078-Bell-Barn-Restoration-473-Dan-Loran-Dec-03,-2009

Read More
c0080-Bell-Barn-Restoration-475-Heaters-Going-Inside-Dan-Loran-Dec-04,-2009
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0080-Bell-Barn-Restoration-475-Heaters-Going-Inside-Dan-Loran-Dec-04,-2009

Read More
c0097 Bell Barn Restoration 502 Dan Loran 16 Dec 2009
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0097 Bell Barn Restoration 502 Dan Loran 16 Dec 2009

16 December 2009 - It is bitterly cold in southern Saskatchewan, with the temperature around the -30 to -40 C range, and wind chills a low as -50. Feels like mid-February.

Read More
c0101-Bell-Barn-Restoration-506-Dan-Loran-Dec-21,-2009
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0101-Bell-Barn-Restoration-506-Dan-Loran-Dec-21,-2009

Read More
c0105-Bell-Barn-Restoration-510-Dan-Loran-Dec-21,-2009
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0105-Bell-Barn-Restoration-510-Dan-Loran-Dec-21,-2009

Read More
c0114-Bell-Barn-Restoration-5232-Dan-Loran-4-Jan,-2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0114-Bell-Barn-Restoration-5232-Dan-Loran-4-Jan,-2010

Read More
c0131 Bell Barn Restoration 5642 Dan Loran 14 Jan 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0131 Bell Barn Restoration 5642 Dan Loran 14 Jan 2010

14 January 2010 - With the onset of some milder weather, the carpenters are able to install roofing paper on the Cottage Washroom.

Read More
c0138 Bell Barn Restoration 5711 Dan Loran 18 Jan 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0138 Bell Barn Restoration 5711 Dan Loran 18 Jan 2010

18 January 2010 - Carpenters install plywood sheathing on the walls of the back storage room in the Cottage Washroom.

Read More
c0148Bell Barn Restoration 5871 Dan Loran 20 Jan 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0148Bell Barn Restoration 5871 Dan Loran 20 Jan 2010

20 January 2010 - The exterior of the Cottage Washroom and Maintenance Building after installation of the front windows.

Read More
c0166 Bell Barn Restoration 793 25 March 2010 Dan Loran
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0166 Bell Barn Restoration 793 25 March 2010 Dan Loran

25 March 2010 - A crew from Bonkowski Enterprises in Wapella starts to install the sheet metal roof on the Cottage washroom.

Read More
c0171 Bell Barn Restoration 798 25 March 2010 Dan Loran
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0171 Bell Barn Restoration 798 25 March 2010 Dan Loran

25 March 2010 - Sheet metal is cut to size for installation on the Cottage Washroom roof.

Read More
c0172 Bell Barn Restoration 799 25 March 2010 Dan Loran
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0172 Bell Barn Restoration 799 25 March 2010 Dan Loran

25 March 2010 - Metal sheets being installed on the roof of the Cottage Washroom.

Read More
c0175 Bell Barn Restoration 809 Dan Loran 29 March 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0175 Bell Barn Restoration 809 Dan Loran 29 March 2010

29 March 2010 - A painter start to paint the interior walls of the Cottage Washroom-Maintenance Building.

Read More
c0176 Bell Barn Restoration 810 Dan Loran 29 March 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0176 Bell Barn Restoration 810 Dan Loran 29 March 2010

29 March 2010 - Getting the door frames ready for painting in the Cottage Washroom.

Read More
c0180 Bell Barn Restoration 814 Dan Loran 29 March 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0180 Bell Barn Restoration 814 Dan Loran 29 March 2010

29 March 2010 - Mixing paint for use inside the Cottage Washroom-Maintenance Building.

Read More
c0192-Bell-Barn-Restoration-922-Very-Rainy-&-Windy-Dan-Loran-13-April-2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0192-Bell-Barn-Restoration-922-Very-Rainy-&-Windy-Dan-Loran-13-April-2010

Read More
c0194 Bell Barn Restoration 930 Dan loran 15 April 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0194 Bell Barn Restoration 930 Dan loran 15 April 2010

15 April 2010 - A furnace will keep the Cottage Washroom-Maintenance Building heated to a minimum lever during the winter months

Read More
c0196 Bell Barn Restoration 932 Dan Loran 15 April 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0196 Bell Barn Restoration 932 Dan Loran 15 April 2010

15 April 2010 - Carpenters begin applying the Hardi-Plank exterior siding to the Cottage Washroom-Maintenance building.

Read More
c0197 Bell Barn Restoration 936 Dan Loran 19 April 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0197 Bell Barn Restoration 936 Dan Loran 19 April 2010

19 April 2010 - Metal guides help ensure that the Hardi-Plank board are installed at the same level as the siding is applied.

Read More
c0200 Bell Barn Restoration 954 Dan Loran 22 April 2010
Lesia Design Inc. 2022-09-15 Lesia Design Inc. 2022-09-15

c0200 Bell Barn Restoration 954 Dan Loran 22 April 2010

22 April 2010 - The Cottage Washroom-Maintenance Building is now fully sided with horizontal Hardi-Planks.

Read More
Newer Posts
Older Posts
Donate & Volunteer

Location

SK-56
Indian Head, SK
S0G 2K0

Hours of Operation

Open daily May long weekend to September long weekend
10:00am-4:30pm

Contact

(306) 695-2355
bellbarnsociety@gmail.com

Contact Us
Employment

Mailing

P.O. Box 1559,
Indian Head, SK
S0G 2K0

Squarespace Website Design by Lesia Design & Digital